Project Title

Installation of Temporary Storage Tanker (TST)

Project Image 1
Project Image 2
Project Image 3
Project Image 4

Project Details

End Client Medco E&P Natuna Ltd
Period 2018
Contractor Fendercare AP Pte Ltd
James Fisher Offshore Terminal Services
Location South Natuna Sea Block-B
Water Depth 70-80m
Work Scope
  1. Pre-lay, installation and hook-up of Conventional Buoy Mooring (CBM)
    • 4 x 12Te anchors, 4 x 76mm x 200m mooring chain
    • 4 x 72mm x 150m steel wire rope
    • 4 x 6Te CBM with QRH
  2. Pre-lay, installation and commissioning
    • 6” x 700m flexible flowline

What We Did

Expertise
Transportation & Installation
Hook-Up & Commissioning
Decommissioning
Marine Consultancy & Services
Services
Tender Support
Project Management
Engineering & Design
Operations & Logistic Support
Manpower Supplies